What’s being developed in Ziegelbrücke
Eight major construction and planning projects will shape the coming years (as of 14 November 2026)
Expansion of the vocational school campus
A new classroom wing and a triple competition sports hall replacing the old gymnasium.
- Cost: around CHF 38 million
- Architecture: Diagonal Architekten AG ("Comparsa")
- Status: foundation stone laid on 2 October 2026
- Completion: planned for the end of 2027
More details
For around CHF 38 million, a new two-storey classroom wing is being built (partly to merge with the Bildungszentrum Gesundheit und Soziales healthcare and social-care school) along with a triple competition sports hall, partly sunk into the ground, replacing the old gymnasium, both fitted with photovoltaic panels. Architecture: Diagonal Architekten AG ("Comparsa"). The final building permits were granted in early 2026. Demolition of the old gymnasium began in early May 2026, and the foundation stone was laid on 2 October 2026. A temporary air-supported hall keeps sports lessons running in the meantime. The timber structure goes up from spring 2027, with completion planned for the end of 2027.
SBB: renewal of station infrastructure
New overhead line equipment, LED lighting and public-address systems at the station.
- Cost: around CHF 25 million
- Construction: June 2024 to autumn 2027
- Night work: 7 April to 4 December 2026
- Closures: occasional, with rail-replacement buses
More details
SBB is replacing the outdated overhead line equipment at Ziegelbrücke station for around CHF 25 million, and installing new LED lighting and public-address systems on the platforms. Construction runs from June 2024 until the project ends in autumn 2027; since June 2025 there have been occasional weekend and full closures with rail-replacement buses. Extensive night work on the platform roof, masts and overhead lines is taking place between April and December 2026.
"Hof" housing development (148 apartments)
Two seven-storey residential buildings between the vocational school and the Jenny site.
- Developer: Fritz+Caspar Jenny AG
- Size: 148 rental apartments, 1.5 to 5.5 rooms
- Architecture: Knorr & Pürckhauer Architekten
- Construction: in two phases
More details
On the plot between the vocational school and the Jenny site, Fritz+Caspar Jenny AG is planning two seven-storey residential buildings (each about 75 × 21 metres) with a total of 148 rental apartments ranging from 1.5 to 5.5 rooms. The invited competition was won by Knorr & Pürckhauer Architekten together with Gersbach Landschaftsarchitektur; construction is planned in two phases.
Südostschweiz report →
Jenny site master plan
The largest contiguous development site in the Canton of Glarus.
- Size: around 30 hectares
- Use: housing, business, education, possibly a hotel
- Master plan: Blättler Dafflon Architekten with Tony Fretton Architects
- Status: planning and legal process underway
More details
Across around 30 hectares, the largest contiguous development site in the Canton of Glarus is taking shape: a high-quality, sustainable mixed-use development combining housing, business, education and possibly a hotel, incorporating the listed factory buildings. The master-plan competition was won by Blättler Dafflon Architekten together with Tony Fretton Architects; the planning and legal process is underway.
Ziegelbrückstrasse framework plan
The framework plan aims to preserve the village character of Ziegelbrückstrasse.
- Approved: spring 2025, municipality of Glarus Nord
- Reason: increasing construction activity
- Purpose: binding on the authorities, guidance for prospective builders and permit authorities
More details
In spring 2025, the municipality of Glarus Nord approved a framework plan for Ziegelbrückstrasse. The reason is increasing construction activity driven by more generous building rights under the revised zoning plan. The framework plan aims to preserve the street's existing village character. It is binding on the authorities and serves as guidance for prospective builders and permit authorities.
New riding stable by the Glarner Gemeinnützige
A new riding stable with a riding hall, outdoor arena and tenant farmer's flat north of Koloniegut 6.
- Developer: Glarner Gemeinnützige
- Use: horse boarding and therapeutic riding
- Budget: CHF 3.53 million
- Status: building application published on 6 May 2026, ready for execution by June 2026
More details
North of Koloniegut 6, the charitable association Glarner Gemeinnützige is planning a new riding stable with a riding hall, outdoor arena and a tenant farmer's flat, intended for horse boarding and therapeutic riding. A precondition was the Glarus Nord zoning plan, which the canton has approved. The building application was published in the cantonal gazette on 6 May 2026, and building profiles are in place on site. The board approved a budget of CHF 3.53 million and set up a building committee; by June 2026 the project was ready for execution. The existing, dilapidated stable will only be demolished once the new facility is finished.
Glarner Gemeinnützige (German) →
LinthWind wind farm (contested, outcome open)
Wind farm on the Linth plain near Bilten, not far from Ziegelbrücke.
- Suitable areas: Bilten Ost 139 ha, Bilten West 63 ha (area profiles June 2026; Bilten West now only a preliminary orientation)
- Minimum distance from residential zones: 500 instead of 300 metres
- Petition: 4,246 signatures, February 2026
- Status: not approved; next the Landrat committee, then the Landrat; federal approval still required
More details
From 2010, utility SAK planned a wind farm on the Linth plain near Bilten, not far from Ziegelbrücke. In 2019 the Glarus cantonal parliament (Landrat) removed the required wind zone from the structure plan by 30 votes to 24. The cantonal structure plan amendment of 2024 put wind power at Bilten back on the table, according to reports at the time with 12 turbines and thus considerably more than in the original SAK project, some up to 200 metres tall. In February 2026 the association "LinthGegenwind" handed a petition with 4,246 signatures to the president of the Landrat. On 29 September 2026 the cantonal government passed the revised structure plan amendment on to the Landrat: the minimum distance from residential zones rises from 300 to 500 metres, the suitable areas Bilten Ost and Bilten West shrink accordingly, and Bilten West is now only listed as a preliminary orientation ("Vororientierung"). According to the opposition group LinthGegenwind, the proposal now provides for eight turbines (nau.ch, 9 November 2026). Next, the Landrat committee will discuss it, then the Landrat decides, and the federal government must approve; unlike the other projects on this page, this one is not approved.
glarus24 report on the petition (German) →
glarus24 report on the government proposal (German) →
Opposition's position: LinthGegenwind (German) →
Axpo/SAK: Power line goes underground
In Ziegelbrücke, SAK and Axpo are moving a 2.4 km overhead line underground.
- Developers: SAK and Axpo
- Location: Ziegelbrücke
- Goals: supply reliability, lower maintenance costs, landscape view
- Linth-plain upgrade: about 19 km in three stages, final stage by 2027, over CHF 4 million
More details
In Ziegelbrücke, SAK and Axpo are jointly moving a 2.4 km overhead line underground. It is part of optimising the grid between the Grynau and Niederurnen substations: SAK is replacing about 19 km of overhead lines on the Linth plain with underground cables in three stages (Uznach–Benken 2016–2018, Benken–Rieden/Schänis under construction, Schänis–Niederurnen planned by 2027), investing over CHF 4 million. The goals are greater supply reliability, lower maintenance costs and a better landscape. Separately, Axpo is converting the line between its Grynau substation in Uznach and Tuggen to 110 kV with a new underground cable, in two steps in 2025 and 2027.